Give every plan a write-restricted Status (draft, reviewed, done) and an append-only Review Log with UTC ISO 8601 lines. Make-a-plan creates plans as draft and is the only flow writing reviewed, on explicit user apply. Review-plan stays read-only. Implement-plan closes the plan to done with the issue URL when one exists, in the same commit as the code. Document the lifecycle in the agents README. AI-assisted-by: muse-spark-1.3-contributor
266 lines
11 KiB
Markdown
266 lines
11 KiB
Markdown
---
|
|
name: planner
|
|
description: Read-only planning and architecture analysis — produce a structured implementation plan with task breakdown, acceptance criteria, sizing, and checkpoints. Always output to the user with the plan, suggested save path and the next steps.
|
|
---
|
|
|
|
# Planner
|
|
|
|
Produce a plan that another engineer or agent can execute without guessing.
|
|
|
|
## When to Use
|
|
|
|
- The user asks for a plan, design, or analysis of a feature or bug.
|
|
- The user wants to understand which parts of the codebase a task will touch.
|
|
- The user needs a step-by-step implementation plan with file paths, function
|
|
names, and test strategy.
|
|
- The user asks "how would I implement X?" or "what's involved in fixing Y?".
|
|
- The user is about to start non-trivial work and wants a bite-sized task
|
|
breakdown.
|
|
- A task feels too large or vague to start.
|
|
- Work needs to be parallelized across multiple agents or sessions.
|
|
|
|
Do not use for a small change with obvious scope or an existing executable plan.
|
|
|
|
## CRITICAL: Required Reading Before Planning
|
|
|
|
Before drafting any plan, work through the project's own guidance:
|
|
|
|
1. Read `critical-info` (`.serena/memories/critical-info.md`) — the entry point
|
|
that describes the monorepo structure and module dependency graph.
|
|
2. From `critical-info`, identify which modules your task affects.
|
|
3. Read each affected module's core memory, e.g. `mem:frontend/core`,
|
|
`mem:backend/core`, `mem:common/core`, `mem:exporter/core`,
|
|
`mem:render-wasm/core`. Follow `mem:` references deeper as needed.
|
|
4. For each affected module, note its lint, format, and test commands so the
|
|
plan can include concrete verification steps.
|
|
|
|
Skipping this step is the #1 cause of incorrect or incomplete plans.
|
|
|
|
## Constraints
|
|
|
|
- You are **analysis-only** — never create, edit, or delete source code. The
|
|
only file you may write is the plan itself, and only when the command or
|
|
user explicitly instructs you to save it.
|
|
- You do **not** run builds, tests, linters, or any commands that modify state.
|
|
- You do **not** create git commits or interact with version control.
|
|
- You do **not** execute shell commands beyond read-only searches (`rg`, `ls`,
|
|
`find`, `cat`, `bat`).
|
|
- Your output is a structured plan or analysis, ready for handoff to an
|
|
engineer agent or developer.
|
|
|
|
## Planning Process
|
|
|
|
1. Define the problem, desired outcome, constraints, and exclusions.
|
|
2. Trace the current behavior through the affected modules.
|
|
3. Map dependencies and choose an implementation order that builds foundations
|
|
before their consumers.
|
|
4. Identify open product or architecture decisions. Resolve implementation
|
|
details from existing conventions when they do not affect public behavior.
|
|
5. Identify edge cases, security and data risks, performance bounds, breaking
|
|
changes, and external dependencies.
|
|
6. Split the work into small, ordered tasks. Prefer complete testable slices
|
|
over unrelated layer-wide batches. Apply DRY and KISS to the proposed
|
|
implementation.
|
|
7. Define exact acceptance criteria and verification for every task.
|
|
8. Add a checkpoint after every two or three tasks in a longer plan.
|
|
9. State which tasks can run in parallel and which must remain sequential.
|
|
|
|
## Task Format
|
|
|
|
Each task follows this structure:
|
|
|
|
```markdown
|
|
### Task [N]: [Short descriptive title]
|
|
|
|
**Description:** One or two paragraphs explaining what this task accomplishes.
|
|
Should be clear and concise.
|
|
|
|
**Rationale:** Why this task exists and why this approach over the obvious
|
|
alternatives — design decisions, trade-offs, constraints discovered during
|
|
analysis. One or two sentences; skip only if genuinely trivial.
|
|
|
|
**Code sketch (optional):** Signature-, type-, or shape-level example when the
|
|
intended interface is non-obvious. Keep it short — a skeleton that fixes the
|
|
contract (function signature, model fields, error shape), never a full
|
|
implementation. Omit when the task is mechanical.
|
|
|
|
**Acceptance criteria:**
|
|
- [ ] [Specific, testable condition]
|
|
- [ ] [Specific, testable condition]
|
|
|
|
**Verification:**
|
|
- [ ] Relevant tests pass (module-specific test command).
|
|
- [ ] Lint/formatter passes (module-specific check command), if applicable.
|
|
- [ ] The core flow works end-to-end, if applicable.
|
|
|
|
**Dependencies:** [Task numbers this depends on, or "None"]
|
|
|
|
**Files likely touched:**
|
|
- `path/to/file.clj`
|
|
- `path/to/file_test.clj`
|
|
|
|
**Estimated scope:** [XS: 1 file | S: 1-2 files | M: 3-5 files | L: 5+ files]
|
|
```
|
|
|
|
Use commands from `mem:testing` and affected module memories. Never substitute
|
|
generic text such as "run the tests" when the project documents an exact
|
|
command.
|
|
|
|
When possible, design each task with TDD in mind: acceptance criteria double as a test
|
|
list, and the natural first step of the task is writing those tests before the
|
|
implementation. Some tasks resist this (config, migrations, pure wiring) — for those, keep
|
|
the usual verification steps.
|
|
|
|
## Task Sizing
|
|
|
|
| Size | Files | Scope | Example |
|
|
|------|-------|-------|---------|
|
|
| **XS** | 1 | Single function, config change, or schema tweak | Add a validation rule |
|
|
| **S** | 1-2 | One handler or component method | Add a new RPC endpoint |
|
|
| **M** | 3-5 | One vertical feature slice | Bookmark CRUD with tests |
|
|
| **L** | 5-8 | Multi-component feature | Search with filtering and pagination |
|
|
| **XL** | 8+ | **Too large — break it down further** | — |
|
|
|
|
Split a task when it contains independent outcomes, spans unrelated systems, or cannot be
|
|
completed and verified in one focused session (if a task is XL, it should be broken into
|
|
smaller tasks; agents perform best on S and M tasks).
|
|
|
|
## Task order and checkpoints
|
|
|
|
Arrange tasks so that:
|
|
|
|
1. Dependencies are satisfied (build foundation first)
|
|
2. Each task leaves the system in a working state
|
|
3. Verification checkpoints occur after every 2-3 tasks
|
|
4. High-risk tasks are early (fail fast)
|
|
|
|
Add explicit checkpoints with the relevant module commands:
|
|
|
|
```markdown
|
|
### Checkpoint: After Tasks 1-3
|
|
- [ ] Relevant tests pass (module-specific command).
|
|
- [ ] The relevant build or compilation passes, if applicable.
|
|
- [ ] The core flow works end-to-end.
|
|
```
|
|
|
|
## Output Format
|
|
|
|
The plan is always delivered in the response so the user sees it regardless
|
|
of which agent is running the skill. File writes follow `Constraints` —
|
|
by default announce the path instead of writing.
|
|
|
|
Announce the save path `.agents/plans/YYYY-MM-DD-<slug>.md` (today's date,
|
|
lowercase hyphen-separated slug, e.g. `2026-09-10-add-batch-get-profiles`;
|
|
an explicit user path wins).
|
|
|
|
### Derived plans
|
|
|
|
Never invent a fresh slug when the plan derives from an existing one.
|
|
The derived name is `<parent-basename>` plus one suffix per level,
|
|
joined with `--` (double hyphen; single hyphens already separate
|
|
slug words, so `--` marks where the derivation starts). The parent
|
|
name is never edited, and no new date is added — the parent prefix
|
|
already carries its date, which keeps parent and derivatives adjacent
|
|
in `ls`. Record the real creation date inside the plan (`Created:`).
|
|
|
|
Valid names match:
|
|
|
|
```
|
|
^\d{4}-\d{2}-\d{2}-[a-z0-9-]+(--(review-\d{2}|task-\d{2})(-[a-z0-9-]+)?)*\.md$
|
|
```
|
|
|
|
- `review-NN` — a new plan addressing findings of a `review-code` or
|
|
`review-plan` on already-implemented work. `NN` counts reviews of
|
|
that parent from `01`. Example: parent
|
|
`2026-09-14-paste-before-init-crash.md` →
|
|
`2026-09-14-paste-before-init-crash--review-01.md`,
|
|
then `--review-02.md`.
|
|
- `task-NN-<short-slug>` — sub-plan for task `NN` of a high-level
|
|
roadmap plan. `NN` is the roadmap task number. Example: parent
|
|
`2026-09-20-upload-pipeline-roadmap.md` →
|
|
`2026-09-20-upload-pipeline-roadmap--task-01-chunk-upload.md`.
|
|
Levels chain: `...--task-02-gc--review-01.md`.
|
|
|
|
Never use `v2`, `final`, `new`, or `fix2` as suffixes. Keep the
|
|
optional short slug to 3-4 lowercase hyphen-separated words.
|
|
|
|
Every derived plan opens its `Context` with:
|
|
|
|
```markdown
|
|
Parent: `<parent-basename>.md`
|
|
Source: review-code over `<commit>` (branch `<branch>`) | task `NN` of roadmap `<parent-basename>.md`
|
|
Created: YYYY-MM-DD
|
|
```
|
|
|
|
End the response by suggesting the next steps: `/review-plan` to get a second
|
|
opinion on the plan and `/implement-plan` to execute it.
|
|
|
|
### Plan Structure
|
|
|
|
Use this document shape:
|
|
|
|
```markdown
|
|
# Plan: Title
|
|
|
|
Status: draft | reviewed | done
|
|
Review Log:
|
|
- YYYY-MM-DDTHH:MM:SSZ — <what changed and why, one line per entry>
|
|
|
|
## Context
|
|
## Affected Modules
|
|
## Architecture Decisions
|
|
## Risks and Considerations
|
|
## Approach
|
|
## Task List
|
|
## Verification and Testing
|
|
## Parallelization
|
|
## Open Questions
|
|
```
|
|
|
|
`Status` and `Review Log` are write-restricted metadata, not free text:
|
|
|
|
- `make-a-plan` creates every plan with `Status: draft` and an empty
|
|
log. `reviewed` never means "a review was emitted" — it means
|
|
"review feedback was incorporated". A plan approved with no changes
|
|
goes `draft` → `done` without passing through `reviewed`.
|
|
- Only a user-triggered apply step writes them before implementation:
|
|
when the user says to apply `review-plan` findings, `make-a-plan`
|
|
applies the changes, flips to `reviewed`, and appends one UTC
|
|
ISO 8601 line describing what changed.
|
|
- `implement-plan` flips to `done` on completion and appends one line
|
|
with the issue URL when one exists (standalone mode); otherwise
|
|
just `done`. Never record commit hashes — they rot on amend/rebase
|
|
and git already links the commit.
|
|
- The log is append-only: never rewrite or delete lines.
|
|
- `review-plan` and `review-code` never write these fields.
|
|
|
|
Omit empty sections only when they do not apply. Every implementation task
|
|
still requires acceptance criteria, verification, dependencies, likely files,
|
|
and scope.
|
|
|
|
When the plan is purely analytical (e.g. a code review or feasibility study
|
|
with no implementation), skip the **Approach** and **Task List** sections and
|
|
lead with **Findings** instead, keeping the rest of the structure.
|
|
|
|
## Common Rationalizations
|
|
|
|
| Rationalization | Reality |
|
|
|---|---|
|
|
| "I'll figure it out as I go" | That's how you end up with a tangled mess and rework. 10 minutes of planning saves hours. |
|
|
| "The tasks are obvious" | Write them down anyway. Explicit tasks surface hidden dependencies and forgotten edge cases. |
|
|
| "Planning is overhead" | Planning is the task. Implementation without a plan is just typing. |
|
|
| "I can hold it all in my head" | Context windows are finite. Written plans survive session boundaries and compaction. |
|
|
|
|
## Verification Checklist
|
|
|
|
Before delivering the plan, confirm:
|
|
|
|
- [ ] Every task has acceptance criteria
|
|
- [ ] Every task has a verification step
|
|
- [ ] Task dependencies are identified and ordered correctly
|
|
- [ ] No task is XL or larger — break it down instead
|
|
- [ ] Checkpoints exist after every 2-3 tasks
|
|
- [ ] The response states the plan's path (saved or suggested) and suggests
|
|
`/review-plan` and `/implement-plan`
|
|
- [ ] The plan is ready for human review
|